We broke ground on November 29th, 2017. The idea was (and still is, I guess) to build the addition ourselves so that we would appreciate every little bit that was added. If we hired it out, we could leave for a week, come back and it would be complete! But would we appreciate that?
After 4 years, I think we would have been just fine. 🙂


11/24/2017 11/29/20 – Propane line moved 11/30/2017 – Owen fulfilling childhood dream (driving an excavator) 12/14/2017 – Pouring footer 4/26/2018 – Had to wait for spring 6/2/2018 – Had to dig more out 8/19/2018 – Took so long to move the A/C, grass grew in. 8/23/2018 8/30/2018 8/9/2018 – Had to match the height to the existing house 9/8/2018 9/9/2018 9/26/2018 – Thank you Michael for helping me with the roof framing! 9/27/2018 – House addition / play stage for the girls 9/29/2018 – I got it straightened out eventually. 10/21/2018 – Sheathing 11/11/2018 11/22/2018 – Thanksgiving 3/9/2019 – Roof installed, cut into the house! 5/10/2019 – Pause to build porch and install hot tub 9/14/2019 9/14/2019 Reworked plumbing for the old house 9/26/2019 – Windows! 10/12/2019 – More windows! 11/23/2019 – Happy Thanksgiving! 11/25/2019 – Cut into second floor 11/26/2019 – Interior framing 11/27/2019 Upgraded electrical service 11/28/2019 – Wiring in the crawlspace 12/21/2019 – Testing the lights! 2/7/2020 Addition waste plumbing 2/9/2020 – Tied into existing waste line 2/29/2020 Soffits, gable work 4/26/2020 5/24/2020 6/2/2020 – Filling in the old well pit 6/23/2020 Master shower 6/27/2020 Upstairs shower 6/27/2020 Utilities transition from old house to new 6/28/2020 Gluing the shower 7/1/2020 New water supply complete! 8/7/2020 Drywall complete 8/8/2020 Priming 8/13/2020 Flooring 8/15/2020 Pause to refinish old house flooring 8/15/2020 Repairs 8/16/2020 – Filler 8/19/2020 Mini Split! 8/20/2020 – Mini split installed 8/20/2020 Mini split installed 8/27/2020 8/28/2020 8/28/2020 8/30/2020 9/2/2020 9/5/2020 – Needed a new front porch… 9/19/2020 Upstairs bathroom floor 9/19/2020 Fixtures 10/3/2020 Bedroom floor 10/17/2020 – Ikea wardrobes 10/23/2020 11/29/2020 Coat closet 12/5/2020 – Siding 12/19/2020 1/20/2021 Carpet! 1/20/2021 1/20/2021 1/20/2021 Office / guest room 1/21/2021 Play room with opening to addition 1/21/2021 Second floor hallway 1/21/2021 Second floor office / guest room